2025 Road & Bridge Construction Program
Overview


Project Summary

- 66 total projects including road reconstruction, bridge reconstruction, road resurfacing, traffic safety improvements, intersection improvements and preventative maintenance.
- 5 bridge replacement
- 22 miles of pavement resurfacing projects, such as reclaim overlay, mill overlay and overlays.
- 79 miles of preventative maintenance projects such as chip sealing and scrub sealing.
- 2.4 miles of full urban and rural road reconstruction.
- 30 miles of GRIP projects (Gravel Road Investment Program).
- Add additional gravel road surfacing, grading and surface stabilization.
- Safety improvement projects:
- High Friction Surface Treatments (HFST) on various county highway curves.
- Construct J-Turn at intersection of TH 169 and CSAH 25.
- Construct turn lanes on TH 37 at the intersection with CSAH 137 (Spirit Lake Rd.).
- Construct turn lanes on CSAH 21 at the intersection with CSAH 138 (Levander Rd.) and CR 656 (Lehto Rd.).
- Construct J-Turn at intersection of TH 169 and CSAH 109 (Nicols Ave.) and CSAH 103 (Mud Lake Rd.).