About this Project
The St. Louis County Public Works Department has a proposed project on St. Louis River Road (CR 696) from Canosia Road (CSAH 98) to Midway Road (CSAH 13) scheduled for construction between July 7 and September 27 of this year. The scope of the project is a full depth reclaim & overlay.
Project Location
On St. Louis River Rd (CR 696) from Canosia Rd (CSAH 98) to Midway Rd (CSAH 13)
Traffic Impacts
There will be no detour and all work will be completed under traffic.
Property Access Details
This project will be performed with a road closure. Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
During the placement of curb and gutter, concrete sidewalk, and concrete driveways, vehicular access to your property will be limited. The Contractor will contact you prior to any disruptions to access to your property to discuss the details on where to park.
If you would like to have any additional work performed on your driveway, yard, or sidewalk, please contact the Contractor directly.
Mailboxes
As part of St. Louis County’s safety policy, new mailbox supports & mailboxes meeting the Federal crash guidelines will be installed by the Contractor. The new mailbox will be installed in approximately the same location as your existing mailbox. The old supports & mailboxes will be deposited next to your driveway for possible salvage by the owners. About 2 weeks after installation of the new supports & mailboxes, any supports & mailboxes not salvaged by the property owner will be picked up for disposal.
About this Project
The St. Louis County Public Works Department has a proposed project on St. Louis River Road (CR 696) from Canosia Road (CSAH 98) to Midway Road (CSAH 13) scheduled for construction between July 7 and September 27 of this year. The scope of the project is a full depth reclaim & overlay.
Project Location
On St. Louis River Rd (CR 696) from Canosia Rd (CSAH 98) to Midway Rd (CSAH 13)
Traffic Impacts
There will be no detour and all work will be completed under traffic.
Property Access Details
This project will be performed with a road closure. Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
During the placement of curb and gutter, concrete sidewalk, and concrete driveways, vehicular access to your property will be limited. The Contractor will contact you prior to any disruptions to access to your property to discuss the details on where to park.
If you would like to have any additional work performed on your driveway, yard, or sidewalk, please contact the Contractor directly.
Mailboxes
As part of St. Louis County’s safety policy, new mailbox supports & mailboxes meeting the Federal crash guidelines will be installed by the Contractor. The new mailbox will be installed in approximately the same location as your existing mailbox. The old supports & mailboxes will be deposited next to your driveway for possible salvage by the owners. About 2 weeks after installation of the new supports & mailboxes, any supports & mailboxes not salvaged by the property owner will be picked up for disposal.
Page last updated: 08 Apr 2025, 08:59 AM
Anticipated Timeline
Project Start Date: July 7, 2025
St. Louis River Rd (CR 696) - Reclaim & Overlay is currently at this stage
Project End Date: September 27, 2025
this is an upcoming stage for St. Louis River Rd (CR 696) - Reclaim & Overlay
Construction will occur from July to September in 2025 on St. Louis River Road between Canosia Rd and Midway Rd. Construction will be occurring between 7:00 am and 7:00 pm Monday through Friday, and between 7:00 am and 5:00 pm on Saturdays. No work will occur on Sundays.
How will I get to my house if I live on this section of roadway?
Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
Who do I contact if I would like additional work performed on my driveway, yard, or sidewalk?
Please contact the Contractor directly for any additional work you would like performed on your driveway, yard, or sidewalk.
How will I know when there will be a disruption in access to my property?
The Contractor will contact you prior to any disruptions to access to your property to discuss the details on where to park.