About this Project
The St. Louis County Public Works Department has a proposed project on CR 232 (Lake Nichols Rd.) from S Shore Dr to TH 53. Road scheduled for construction between July 6 and August 29 of this year. The scope of the project is to replace seven culverts on Lake Nichols Road.
Location
S Shore Dr to TH 53
Traffic Impacts
There will be no detour and all work will be completed under traffic.
Property Access Details
This project will be performed under traffic. Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
If you would like to have any additional work performed on your driveway, yard, or sidewalk, please contact the Contractor directly.
About this Project
The St. Louis County Public Works Department has a proposed project on CR 232 (Lake Nichols Rd.) from S Shore Dr to TH 53. Road scheduled for construction between July 6 and August 29 of this year. The scope of the project is to replace seven culverts on Lake Nichols Road.
Location
S Shore Dr to TH 53
Traffic Impacts
There will be no detour and all work will be completed under traffic.
Property Access Details
This project will be performed under traffic. Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
If you would like to have any additional work performed on your driveway, yard, or sidewalk, please contact the Contractor directly.
Page last updated: 20 Apr 2026, 11:29 AM
Anticipated Timeline
Project Start Date: July 6, 2026
Lake Nichols Rd (CR 232) - Culvert Replacement is currently at this stage
Project End Date: August 29, 2026
this is an upcoming stage for Lake Nichols Rd (CR 232) - Culvert Replacement
Construction will occur from July through August in 2026. Construction will be occurring between 7:00 am and 7:00 pm Monday through Friday, and between 7:00 am and 5:00 pm on Saturdays. No work will occur on Sundays.
How will I get to my house if I live on this section of roadway?
Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
Who do I contact if I would like additional work performed on my driveway, yard, or sidewalk?
Please contact the Contractor directly for any additional work you would like performed on your driveway, yard, or sidewalk.
How will I know when there will be a disruption in access to my property?
The Contractor will contact you prior to any disruptions to access to your property to discuss the details on where to park.