Share Bergquist Rd (CR 258) - Culvert Replacement on FacebookShare Bergquist Rd (CR 258) - Culvert Replacement on TwitterShare Bergquist Rd (CR 258) - Culvert Replacement on LinkedinEmail Bergquist Rd (CR 258) - Culvert Replacement link
About this Project
The St. Louis County Public Works Department has a proposed project on CR 258 (Bergquist Rd.) from Lismore Rd. to Shilhon Rd. scheduled for construction between July 6 and August 29 of this year. The scope of the project is to replace one culvert on Bergquist Road. The culvert is located about 100' north of CR 276 and has been replaced.
Location
CR 276 (Lismore Rd.) & CR 25 (Shilhon Rd.)
Traffic Impacts
Road Closed - No Detour
Property Access Details
This project will be performed with a road closure. Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
If you would like to have any additional work performed on your driveway, yard, or sidewalk, please contact the Contractor directly.
About this Project
The St. Louis County Public Works Department has a proposed project on CR 258 (Bergquist Rd.) from Lismore Rd. to Shilhon Rd. scheduled for construction between July 6 and August 29 of this year. The scope of the project is to replace one culvert on Bergquist Road. The culvert is located about 100' north of CR 276 and has been replaced.
Location
CR 276 (Lismore Rd.) & CR 25 (Shilhon Rd.)
Traffic Impacts
Road Closed - No Detour
Property Access Details
This project will be performed with a road closure. Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
If you would like to have any additional work performed on your driveway, yard, or sidewalk, please contact the Contractor directly.
Page last updated: 20 Apr 2026, 11:29 AM
Anticipated Timeline
Project Start Date: July 6, 2026
Bergquist Rd (CR 258) - Culvert Replacement is currently at this stage
Project End Date: August 29, 2026
this is an upcoming stage for Bergquist Rd (CR 258) - Culvert Replacement
Construction will occur from July through August in 2026. Construction will be occurring between 7:00 am and 7:00 pm Monday through Friday, and between 7:00 am and 5:00 pm on Saturdays. No work will occur on Sundays.
How will I get to my house if I live on this section of roadway?
Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
Who do I contact if I would like additional work performed on my driveway, yard, or sidewalk?
Please contact the Contractor directly for any additional work you would like performed on your driveway, yard, or sidewalk.
How will I know when there will be a disruption in access to my property?
The Contractor will contact you prior to any disruptions to access to your property to discuss the details on where to park.