About this Project
The St. Louis County Public Works Department has a proposed culvert replacement project on CSAH 8 located between Gravell Rd and TH 53 scheduled for construction between June 23 and August 2. The duration of construction will be approximately two weeks during the dates listed above.
Location
CSAH 8 between Gravell Rd and TH 53
Traffic Impacts
A road closure will be permitted for the box culvert on CSAH 8. If the Contractor elects to implement a road closure, signs shall be placed on CSAH 8 at TH 33 and US 53 with the date and location of the proposed closure along with signs at the road closure location indicating the location of the closure facing both directions one week prior to the road closure.
About this Project
The St. Louis County Public Works Department has a proposed culvert replacement project on CSAH 8 located between Gravell Rd and TH 53 scheduled for construction between June 23 and August 2. The duration of construction will be approximately two weeks during the dates listed above.
Location
CSAH 8 between Gravell Rd and TH 53
Traffic Impacts
A road closure will be permitted for the box culvert on CSAH 8. If the Contractor elects to implement a road closure, signs shall be placed on CSAH 8 at TH 33 and US 53 with the date and location of the proposed closure along with signs at the road closure location indicating the location of the closure facing both directions one week prior to the road closure.
Page published: 02 May 2025, 04:03 PM
Anticipated Timeline
Project Start Date: June 23, 2025
CSAH 8 (Hwy 8) - Culvert Replacement is currently at this stage
Project End Date: August 2, 2025
this is an upcoming stage for CSAH 8 (Hwy 8) - Culvert Replacement
Construction will occur for a 2 week period sometime between June 23 and August 2. Construction will be occurring between 7:00 am and 7:00 pm Monday through Friday, and between 7:00 am and 5:00 pm on Saturdays. No work will occur on Sundays.