Project Complete!
About this Project
The St. Louis County Public Works Department has a proposed project on CSAH 6 (Maple Grove Road) from TH 2 to CSAH 13 (Midway Road) scheduled for construction between June 10 and September 21 of this year. The construction will take place in about a 3 week period in this time frame. Maple Grove Road will be closed during construction and a posted detour will be placed utilizing TH 2 and Midway Road. You will always have access to your property, but the direction which you access it will vary throughout the project.
Location
On Maple Grove from TH 2 to CSAH 13 (Midway Road)
Please Note: There is another project near by on St. Louis River Rd. Check the project list for more details.
Traffic Impacts
Maple Grove Road will be closed during construction and a posted detour will be placed utilizing TH 2 and Midway Road. You will always have access to your property, but the direction which you access it will vary throughout the project.
Property Access Details
This project will be performed with a road closure. Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
During the placement of curb and gutter, concrete sidewalk, and concrete driveways, vehicular access to your property will be limited. The Contractor will contact you prior to any disruptions to access to your property to discuss the details on where to park.
If you would like to have any additional work performed on your driveway, yard, or sidewalk, please contact the Contractor directly.
Project Complete!
About this Project
The St. Louis County Public Works Department has a proposed project on CSAH 6 (Maple Grove Road) from TH 2 to CSAH 13 (Midway Road) scheduled for construction between June 10 and September 21 of this year. The construction will take place in about a 3 week period in this time frame. Maple Grove Road will be closed during construction and a posted detour will be placed utilizing TH 2 and Midway Road. You will always have access to your property, but the direction which you access it will vary throughout the project.
Location
On Maple Grove from TH 2 to CSAH 13 (Midway Road)
Please Note: There is another project near by on St. Louis River Rd. Check the project list for more details.
Traffic Impacts
Maple Grove Road will be closed during construction and a posted detour will be placed utilizing TH 2 and Midway Road. You will always have access to your property, but the direction which you access it will vary throughout the project.
Property Access Details
This project will be performed with a road closure. Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
During the placement of curb and gutter, concrete sidewalk, and concrete driveways, vehicular access to your property will be limited. The Contractor will contact you prior to any disruptions to access to your property to discuss the details on where to park.
If you would like to have any additional work performed on your driveway, yard, or sidewalk, please contact the Contractor directly.
Page last updated: 05 Nov 2024, 01:32 PM
Anticipated Timeline
Project Start Date: June 10, 2024
Maple Grove Rd (CSAH 6) - Culvert Replacement has finished this stage
Project End Date: Sept 21, 2024
Maple Grove Rd (CSAH 6) - Culvert Replacement is currently at this stage
The construction will take place in about a 3 week period between June 10 and September 21. Maple Grove Road will be closed during construction and a posted detour will be placed utilizing TH 2 and Midway Road. You will always have access to your property, but the direction which you access it will vary throughout the project. Construction will be occurring between 7:00 am and 7:00 pm Monday through Friday, and between 7:00 am and 5:00 pm on Saturdays. No work will occur on Sundays.
How will I get to my house if I live on this section of roadway?
Houses with no access to a side street will access their homes either by driving through the construction site, or walking on a marked path to their home when road access is not feasible. We will try and keep the amount of time that walking is required to a minimum. Persons with disabilities should contact Steve Krasaway to discuss special accommodations.
How will I know when there will be a disruption in access to my property?
The Contractor will contact you prior to any disruptions to access to your property to discuss the details on where to park.