Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements
Share Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements on FacebookShare Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements on TwitterShare Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements on LinkedinEmail Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements link
About this Project
St. Louis County is leading an intersection safety improvement project in 2026 on Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) located near Proctor. The project includes the following components:
Lower the profile of Midway Rd by approximately 10 ft to increase intersection sight distance.
Construct left- and right-turn lanes on Midway Rd.
Install roadway lighting to illuminate the intersection.
Replace the guardrail located on Midway Rd, south of N Cloquet Rd.
Funding for this project is provided in part through the
The County Road Safety Plan (CRSP) ranks this intersection five (5) out of 1,488 intersections which places this intersection in the top one (1) percent by risk. The CRSP recommends construction of left- and right-turn lanes. For the five-year period of 2020 through 2024, there were eight (8) reported intersection related crashes. The observed crash rate for this period was 0.526 crashes/million entering vehicles which is greater than the statewide average (0.141 crashes/million entering vehicles) and the critical crash rate (0.420 crashes/million entering vehicles). This crash history is considered statistically significant. An aggravating factor that contributes to these crashes is the hill located immediately south of the intersection on Midway Rd. This hill significantly restricts intersection sight distance which means it is difficult for drivers stopped on N Cloquet Rd to see northbound vehicles on Midway Rd. St. Louis County completed an Intersection Control Evaluation (ICE) of this intersection in 2022. The ICE report also recommended installation of left- and right-turn lanes and lowering the profile of Midway Rd to improve visibility of vehicles on Midway Rd. and are proven safety countermeasures to reduce the risk of serious crashes.
Location
Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45)
Traffic Impacts
There will be no detour and all work will be completed under traffic.
About this Project
St. Louis County is leading an intersection safety improvement project in 2026 on Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) located near Proctor. The project includes the following components:
Lower the profile of Midway Rd by approximately 10 ft to increase intersection sight distance.
Construct left- and right-turn lanes on Midway Rd.
Install roadway lighting to illuminate the intersection.
Replace the guardrail located on Midway Rd, south of N Cloquet Rd.
Funding for this project is provided in part through the
The County Road Safety Plan (CRSP) ranks this intersection five (5) out of 1,488 intersections which places this intersection in the top one (1) percent by risk. The CRSP recommends construction of left- and right-turn lanes. For the five-year period of 2020 through 2024, there were eight (8) reported intersection related crashes. The observed crash rate for this period was 0.526 crashes/million entering vehicles which is greater than the statewide average (0.141 crashes/million entering vehicles) and the critical crash rate (0.420 crashes/million entering vehicles). This crash history is considered statistically significant. An aggravating factor that contributes to these crashes is the hill located immediately south of the intersection on Midway Rd. This hill significantly restricts intersection sight distance which means it is difficult for drivers stopped on N Cloquet Rd to see northbound vehicles on Midway Rd. St. Louis County completed an Intersection Control Evaluation (ICE) of this intersection in 2022. The ICE report also recommended installation of left- and right-turn lanes and lowering the profile of Midway Rd to improve visibility of vehicles on Midway Rd. and are proven safety countermeasures to reduce the risk of serious crashes.
Location
Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45)
Traffic Impacts
There will be no detour and all work will be completed under traffic.
Page last updated: 13 Mar 2026, 01:19 PM
Anticipated Timeline
Funding Awarded - April 2024
Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements has finished this stage
Finalize Construction Plan - November 2025
Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements has finished this stage
Bidding - February 2026
Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements is currently at this stage
Construction - May through September 2026
this is an upcoming stage for Midway Rd (CSAH 13) at N Cloquet Rd (CSAH 45) - Intersection Improvements