Project Updates!

CSAH 25 (Vermilion Dr.) is now in full construction mode. Ulland Brother's (Contractor) started subcutting and backfilling with sand and Class 5 from TH 53 on Wednesday (7/10) working East towards CSAH 24. This will take approximately 2-3 weeks. The road will be closed during this time and the contractor will keep driveway access to homeowners as much as possible.